2023 Phase 4 Roof Project Update

November 10 Update

The final phase 4 roof project is now complete. Site demobilization and demolition of the overhead protection and scaffolding will start on Monday November 13th for a few days weather permitting, elevated noise levels (hammering and banging) are expected during this time.

October 23 Update

Roof work continues this week weather permitting, no elevated noise levels expected.

October 16 Update

Roof work continues this week weather permitting.

October 11 Update

No roof work today due to the forecasted weather

October 2 Update

Roof work continues today and throughout this week weather permitting. Elevated noise levels are expected during this phase as demolition and the removal of roofing material on the new work area on the West of the building (Spadina side) is in effect.

September 27 Update

Roof work continues today and throughout this week weather permitting. Scaffolding staircase construction on Spadina side of the building is in progress and elevated noise levels are expected during the phase .

September 18 Update

Roof work continues today and throughout this week weather permitting, no elevated noise levels are expected.

September 11 Update

Roof work continues today and throughout this week weather permitting, no elevated noise levels are expected.

September 5 Update

Roof work continues today and throughout this week weather permitting with demolition, mobilization and preparation work for lightweight concrete pouring later in the week. Elevated noise levels expected.

August 28 Update

Roof work continues today and throughout this week weather permitting with demolition work and elevated noise levels expected.

August 16 Update

Roof work continues today with demolition work and elevated noise levels expected.

August 15 Update

No roof work due to weather forecast today.

August 14 Update

Roof work continues this week weather permitting, elevated noise levels are expected during this demolition phase.

July 17 Update

Roof work continues today and tomorrow in the final stages of demobilization and cleanup of the Phase 3 project.

May 8 Update

Roof work continues today and throughout this week, no elevated noise levels are expected.

May 2 Update

Roof work continues today and throughout this week, no elevated noise levels are expected.

April 28 Update

Roof work continues tomorrow Saturday April 29th with the installation safety railings on the overhang portion of the roof over Harbord St. Harbord St will be closed to traffic, please follow all posted signs at street level for alternative walking routes. Work will start at 9am and anticipated noise levels will be limited to the use of drills and light duty equipment. This part of the roof does not have occupied student spaces under it.

February 13 Update

Roof work continues today Monday and this week with the installation of metal flashing along perimeter walls

February 10 Update

Roof work continues today with the installation of metal flashing along perimeter walls

February 8 Update

Roof work continues today with the installation of metal flashing along perimeter walls

January 26 Update

Dismantling of the overhead protection scaffolding on the sidewalk of Spadina Ave will continue on January 27th starting at 9am. Elevated noise is expected during this time.

January 25 Update

Overhead protection scaffolding is scheduled to be removed on the Spadina side of our building weather permitting on January 26th or 27th. Elevated noise is expected during the dismantling process. Work is expected to start at 9 am.

January 16 Update

Roof work continues today and continues this week weather permitting with the installation of metal flashing around the perimeter walls

December 8 Update

No scheduled work today as the contractor enters the next phase in wrapping up the project

December 7 Update

Roof work continues today

December 6 Update

No work today due to the weather forecast

December 5 Update

Roof work continues today

December 4 Update

Roof Work continues on Sunday December 4th starting at 10am

December 02 Update

Roof work continues today

December 01 Update

Roof Work continues today

November 30 Update

Due to the weather no roof work today

November 29 Update

Roof Work continues today

November 28 Update

Roof Work continues today and all week with the final layer of membrane adhesion

November 25 Update

Roof Work continues today

November 24 Update

Roof Work continues today

November 23 Update

Roof Work continues today

November 22 Update

Roof Work continues today

November 21 Update

Due to the weather FORECAST, WITH high winds expected, no work will be carried out today

November 18 Update

Work continues today weather permitting with the adhesion of cap sheet membrane

November 17 Update

Work continues today after the weather delay on November 16 with the clearing of snow and preparation for Cap sheet installation

November 15 Update

Due to weather forecast, limited work will be carried out today. Securing the site will be the focus.

November 14 Update

Work continues today and all week weather permitting with the adhesion of various waterproofing membranes.

November 11 Update

Due to weather no work will be carried out today.

November 11 Update

Due to weather no work will be carried out today.

November 8 Update

Work continues today and all week weather permitting. No elevated noise levels are expected.

November 7 Update

Work continues today with the adhesion of several types of membranes over the poured concrete. No elevated noise levels are expected.

November 4 Update

Work continues today with the adhesion of several types of membranes over the poured concrete. No elevated noise levels are expected. Work is scheduled to continue on Saturday November 5th starting at 10am taking advantage of the warmer weather

November 2 Update

Work continues today and all week with the adhesion of several types of membranes over the poured concrete. No elevated noise levels are expected.

November 1 Update

Work continues today with receiving materials to start on the installation of waterproofing membranes this week.

October 21 Update

Final roof anchors installation between the hours of 9-11am today with elevated noise levels expected (Drilling – Grinding – Hammering) Followed by lightweight concrete pouring today and Saturday Oct 21.

October 20 Update

Work continues today with preparations and delivery of materials for the lightweight concrete pouring scheduled for Friday 21st and Saturday 22nd

October 11 Update

Lightweight concrete pouring scheduled this week Oct 11–14

October 3 Update

NO SCHEDLUDED WORK TODAY

September 30 Update

Work continues today with high noise levels ( hammering) is expected during the working hours due to the removal of concrete curbs

 

September 29 Update

Work continues today with high noise levels ( hammering) is expected during the working hours due to the removal of concrete curbs

 

   September 28 Update

Work continues today with High noise (drilling and hammering) is expected during the working hours due to the roof anchors installation

September 27 Update

NO SCHEDULED WORK TO BE CARRIED OUT TODAY DUE TO WEATHER

September 26 Update

NO SCHEDULED WORK TO BE CARRIED OUT TODAY DUE TO WEATHER

September 22 Update

NO SCHEDULED ROOF WORK ON FRIDAY SEPTEMBER 23RD

September 21 Update

ELEVATED NOISE LEVELS (DRILLING – GRINDING – HAMMERING) WILL CONTINUE SEPTEMBER 21–30 DUE TO THE INSTALLATION OF ROOF ANCHORS

September 14 Update

Starting September 14 – 16 The level of noise will be elevated due to the removal of the existing roof anchors (Grinding and hammering)